SDX Energy Plc (AIM: SDX), the MENA-focused energy company, is pleased to announce the spudding of the SD-12 East appraisal well (SDX WI 75%), targeting additional reserves to the east of the SD-12X discovery well on the Sobhi field located in the Ibn Yunus North development lease. SD-12 East spudded on 16 April 2022 and is expected to reach TD in approximately three weeks.  The primary target, which has already been encountered in the Ibn Yunus and Sobhi reservoirs, is the basal Kafr El Sheikh sand at around 6,480 ft TVDSS. The well is targeting an estimated gross unrisked P50 EUR of 7 Bcf and has a 80% chance of success.  In a success case, SD-12 East will be tied-in to the CPF via the existing SD-12X flow-line and is expected to be on production by mid-July 2022.

 

SD-12 East is the second of three wells to be drilled in the South Disouq area during 2022. The third well in the campaign will be the MA-1X well (Mohsen) targeting an estimated gross unrisked P50 EUR of 21 Bcf. The Mohsen well is planned to spud mid-to-late May.

 

 

Mark Reid, CEO of SDX, commented:

 

"I am pleased to announce the spudding of SD-12 East, the second well in the South Disouq drilling campaign. This campaign is further exploring the potential in the South Disouq area and, with the recent success of the SD-5X discovery well, it has already enabled us to plan for an increase in our production guidance in the coming months. So far in 2022, SDX has had three discoveries from three wells drilled and I look forward to updating the market further as our very busy drilling campaign progresses throughout the year."

 

 

 

About SDX

SDX is an international oil and gas exploration, production, and development company, headquartered in London, United Kingdom, with a principal focus on MENA. In Egypt, SDX has a working interest in two producing assets: a 36.9% operated interest in the South Disouq and Ibn Yunus gas fields and a 67.0% operated interest in the Ibn Yunus North gas field in the Nile Delta and a 50% non-operated interest in the West Gharib concession, which is located onshore in the Eastern Desert, adjacent to the Gulf of Suez. In Morocco, SDX has a 75% working interest in four development/production concessions, all situated in the Gharb Basin. The producing assets in Morocco are characterised by attractive gas prices and exceptionally low operating costs. SDX has a strong weighting of fixed price gas assets in its portfolio with low operating costs and attractive margins throughout, providing resilience in a low commodity price environment. SDX's portfolio also includes high impact exploration opportunities in both Egypt and Morocco.

 

 

For further information, please see the Company's website at www.sdxenergygroup.com or the Company's filed documents at www.sedar.com

 

Competent Persons Statement

In accordance with the guidelines of the AIM Market of the London Stock Exchange and the COGE handbook requirements, the technical information contained in the announcement has been reviewed and approved by Dr Rob Cook, VP Subsurface of SDX. Dr. Cook has 30 years of oil and gas industry experience and is the qualified person as defined in the London Stock Exchange's Guidance Note for Mining and Oil and Gas companies. Dr. Cook holds a BSc in Geochemistry and a PhD in Sedimentology from the University of Reading, UK. He is a Chartered Geologist with the Geological Society of London (Geol Soc) and a Certified Professional Geologist (CPG-11983) with the American Institute of Professional Geologists (AIPG).

 

For further information:

 

SDX Energy Plc

Mark Reid

Chief Executive Officer

Tel: +44 203 219 5640

 

 

 

Stifel Nicolaus Europe Limited (Nominated Adviser and Broker)

Callum Stewart

Jason Grossman

Ashton Clanfield

Tel: +44 (0) 20 7710 7600

 

Camarco (PR)

Billy Clegg/Owen Roberts/Violet Wilson

Tel: +44 (0) 203 757 4980

 


Glossary

 

"WI"

Working interest

"TVDSS"

Total vertical depth subsea

"TD"

Total depth

"P50"

At least a 50% probability that the quantities actually recovered will equal or exceed the best estimate

"MD"

Measured depth

"EUR"

Estimated ultimate recovery

"CPF"

Central processing facility

"Bcf"

Billion cubic feet

 

 

Forward-looking information

 

Certain statements contained in this press release may constitute "forward-looking information" as such term is used in applicable Canadian securities laws. Any statements that express or involve discussions with respect to predictions, expectations, beliefs, plans, projections, objectives, assumptions or future events or are not statements of historical fact should be viewed as forward-looking information. In particular, statements regarding developments at, and the expected results of, the drilling campaign at South Disouq, and the time in which the Company intends to update the market on its production guidance and future results should be regarded as forward-looking information.

 

 

The forward-looking information contained in this document is based on certain assumptions, and although management considers these assumptions to be reasonable based on information currently available to them, undue reliance should not be placed on the forward-looking information because SDX can give no assurances that they may prove to be correct. This includes, but is not limited to, assumptions related to, among other things, commodity prices and interest and foreign exchange rates; planned synergies, capital efficiencies and cost-savings; applicable tax laws; future production rates; receipt of necessary permits; the sufficiency of budgeted capital expenditures in carrying out planned activities, and the availability and cost of labour and services.

 

All timing given in this announcement, unless stated otherwise, is indicative, and while the Company endeavours to provide accurate timing to the market, it cautions that, due to the nature of its operations and reliance on third parties, this is subject to change, often at little or no notice. If there is a delay or change to any of the timings indicated in this announcement, the Company shall update the market without delay.

 

Forward-looking information is subject to certain risks and uncertainties (both general and specific) that could cause actual events or outcomes to differ materially from those anticipated or implied by such forward-looking statements. Such risks and other factors include, but are not limited to, political, social, and other risks inherent in daily operations for the Company, risks associated with the industries in which the Company operates, such as: operational risks; delays or changes in plans with respect to growth projects or capital expenditures; costs and expenses; health, safety and environmental risks; commodity price, interest rate and exchange rate fluctuations; environmental risks; competition; permitting risks; the ability to access sufficient capital from internal and external sources; and changes in legislation, including but not limited to tax laws and environmental regulations. Readers are cautioned that the foregoing list of risk factors is not exhaustive and are advised to refer to the Principal Risks & Uncertainties section of SDX's Annual Report for the year ended 31 December 2021, which can be found on SDX's SEDAR profile at www.sedar.com, for a description of additional risks and uncertainties associated with SDX's business.

 

The forward-looking information contained in this press release is as of the date hereof and SDX does not undertake any obligation to update publicly or to revise any of the included forwardlooking information, except as required by applicable law. The forwardlooking information contained herein is expressly qualified by this cautionary statement.

 

 

Oil and Gas Advisory

Certain disclosures in this news release constitute "anticipated results" for the purposes of National Instrument 51-101 - Standards of Disclosure for Oil and Gas Activities ("NI 51-101") of the Canadian Securities Administrators because the disclosure in question may, in the opinion of a reasonable person, indicate the potential value or quantities of resources in respect of the Company's resources or a portion of its resources. Without limitation, the anticipated results disclosed in this news release include estimates of volume, flow rate, production rates, porosity, and pay thickness attributable to the resources of the Company. Such estimates have been prepared by Company management and have not been prepared or reviewed by an independent qualified reserves evaluator or auditor. Anticipated results are subject to certain risks and uncertainties, including those described above and various geological, technical, operational, engineering, commercial, and technical risks. In addition, the geotechnical analysis and engineering to be conducted in respect of such resources is not complete. Such risks and uncertainties may cause the anticipated results disclosed herein to be inaccurate. Actual results may vary, perhaps materially.

Prospective Resources Data

 

The prospective resources estimates disclosed or referenced herein have been prepared by Dr. Rob Cook, a qualified reserves evaluator, in accordance with the SPE's Canadian Oil and Gas Evaluation Handbook and in accordance with NI 51-101. The prospective resources disclosed herein have an effective date of 1 January 2022. Prospective resources are those quantities of gas, estimated as of the given date, to be potentially recoverable from undiscovered accumulations through future development projects. As prospective resources, there is no certainty that any portion of the resources will be discovered. The chance that an exploration project will result in a discovery is referred to as the "chance of discovery" as defined by the management of the Company.

 

There is no certainty that it will be commercially viable to produce any portion of the resources discussed herein; though any discovery that is commercially viable would be tied back to the Company's pipeline in Morocco and then connected to customers' facilities within 9 to 12 months of discovery. Based upon the economic analysis undertaken on any discovery, management has attributed an associated chance of development of 100%.

 

There are uncertainties associated with the volume estimates of the prospective resources disclosed herein, due to the level of information available on prospective resources, but ranges are defined based on data from the Company's nearby existing analogous wells. Some of the risks and uncertainties are outlined below:

·      Petrophysical parameters of the sand/reservoir;

·      Fluid composition, especially heavy end hydrocarbons;

·      Accurate estimation of reservoir conditions (pressure and temperature);

·      Reservoir drive mechanism;

·      Potential well deliverability; and

·      The thickness and lateral extent of the reservoir section, currently based on 3D seismic data.

 

Inside Information

This announcement does not contain inside information.

 

This information is provided by RNS, the news service of the London Stock Exchange. RNS is approved by the Financial Conduct Authority to act as a Primary Information Provider in the United Kingdom. Terms and conditions relating to the use and distribution of this information may apply. For further information, please contact rns@lseg.com or visit www.rns.com.

RNS may use your IP address to confirm compliance with the terms and conditions, to analyse how you engage with the information contained in this communication, and to share such analysis on an anonymised basis with others as part of our commercial services. For further information about how RNS and the London Stock Exchange use the personal data you provide us, please see our Privacy Policy.
 
END
 
 
MSCBKDBDKBKKCQB
Find out how to deal online from £1.50 in a SIPP, ISA or Dealing account. AJ Bell logo

Related Charts

Sdx Energy PLC (SDX)

+0.12p (+5.95%)
delayed 10:45AM